SITE INSPECTIONS...are they really necessary?


Some see inspections as an unnecessary cost to the construction of their new facility. But for a majority of facilities, general review is mandatory as part of the building permit requirements. Most building codes require professional engineers to undertake a general review of construction of specified buildings and forward written reports from this general review to the chief building official. The purpose of the general review is to ensure that the project is being constructed in “general conformance” with the engineered plans. Your engineering firm should provide a list of inspection requirements, at the completion of the engineered drawings, to ensure that you are aware of when an inspection is to be completed. Stonecrest supplies a list of inspections to both the Owner and the Contractor to ensure none of the required inspections are missed. It is critical that these inspections be completed. Not having the required inspections and reports completed can cause issues with the local municipality such as denied occupancy and forfeited permit deposits.

The inspections you will require for your facility will differ depending on the type of facility you are building. An agricultural storage shed may require a soil/footing inspection, a wall reinforcement inspection, a framing inspection and a final inspection. Whereas a bunker silo may require a soil/footing

inspection, a wall reinforcement inspection and a final inspection. Exceptions may apply to liquid manure storage tank or structures that require fill material to be installed under structural members. In these cases, a geotechnical engineering company may be required to complete additional soil testing prior to continuing construction. For structural onsite inspections, your project may include the following:

Soil and Footings

This first inspection is completed after excavation for the foundation or footings for the facility and prior to concrete being poured into the strip, post or pad footings for the facility. When the site has been completely prepared for the start of construction and the concrete formwork and reinforcing steel have been set for the placement of the footings for the structure, the engineer should be notified to provide an inspection of the soil conditions and footings. This review may be performed provided the ability to inspect either component is not compromised. You should notify the engineer of any concerns with regards to, but not limited to, soil bearing capacity, slope stability, groundwater and drainage. You should also notify the engineer if non-native soils have been used in the site preparation. If your project contains provisions for a liquid manure storage or requires fill material under structural members, a geotechnical engineer must be retained to perform an investigation prior to construction as well as complete a general review of the excavation.

Concrete Reinforcement

This can range in a wide variety of inspections depending on what has been engineered for your facility. These inspections are completed when the reinforcing steel has been tied for the specified concrete components including foundation walls, gutter/pit walls, upper or lower sandwich walls, gutter or reinforced floor slab, pour-in-place suspended slabs or structural beams and suspended poured concrete slabs over basement hallways. Regardless of the component requiring inspection, the engineer should be notified to complete an inspection. As part of a general review, it is unreasonable for the engineer to review the reinforcement each time that concrete is poured. The contractor is responsible for providing the proper reinforcement and placement, as specified in the engineered plans, for components which are not reviewed by your engineer.

Manure Transfer Systems

These mandatory inspections must be completed to comply with Nutrient Management regulations and can encompass transfer system pipes, cantilevered box scrapers or gutters connected to a nutrient management storage, or even the various components designed within a flush transfer system including receiver pits and flush towers. For piston pump piped manure transfers, inspections should be completed once all of the transfer pipes have been installed to review the pipe connections, junction connections, shut off valves and all seals. The contractor should also be available to make any gasket-sealed joint available for inspection. In the case of a concrete transfer system, we strongly recommend to have the footings, walls and lid reinforcement of the system inspected as well.

Framing Inspection

The framing inspection is completed when the facility has been completely framed, prior to completing interior or exterior sheathing that would prevent a visual inspection of key framing components including truss installation, bracing and firestops. Some inspectors will often combine the inspection of the framing components with the final inspection if all the structural components meet compliance with the engineered drawings.

Final Inspection

This inspection is completed when the facility has been substantially completed and all finishes, concrete work, equipment placement, etc., have been completed. In addition, backfill around the facility, installation of safety fencing/gating, monitoring stations, drainage tile and required exiting should be finished. Township building departments will grant occupancy or close the building permit once the Engineer’s approval has been granted in the final report.

Ensuring that your project has the necessary structural inspections completed throughout its construction will ensure building permit and engineering compliance and will allow you to close your building permit and eliminate any issues with occupancy or forfeited permit deposits.


Featured Posts
Archive

2079 Line 34

Shakespeare, Ontario

Canada  N0B 2P0

info@stonecrestengineering.com

 

STONECREST ENGINEERING INC.

Tel: 519.625.8025

TF: 1.855.625.8025

Fax: 519.625.8966

  • White Facebook Icon
  • White Twitter Icon

© 2018 by Stonecrest Engineering Inc.